Muscat Sayarati Co. Uses a job – order costing system with a single plantwide predetermined overhead rate based on labor – hours. The company based

Muscat Sayarati Co. Uses a job – order costing system with a single plantwide predetermined overhead rate based on labor – hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $ 525,000, variable manufacturing overhead of $ 6.00 per labor hour, and 35,000 labor – hours. The job sheet of Job G828 shows that the number of units in this job order is 45 units which incurred total of 90 labor – hours. This job consumed $ 14 / unit of direct materials cost and $ 64 / unit of direct labor costs. What would be the total cost for Job G828 approximately? a. $ 4,860 b. $ 4,455 C. $ 5,400 d. $ 4.185